west java and banten

Banten Province

System Conditions
Electrical systems in the province of Banten is a part of the system interconnection of Java-Madura-Bali. The main supply for electricity demand in the province of Banten other than the transmission system 500 kV and 150 kV are Suralaya power plant, power plant / PLTGU Freshwater Estuary.
Currently electrification ratio of Banten Province reached 63.90% and the ratio of electrified villages is 99.33%. The waiting list has reached U.S. $ 40.340 request or at 304.9 MVA.

Balance of Power
Province of DKI Jakarta, Banten, West Java, Central Java, IN. Yogyakarta, East Java, and Bali have been well interconnected on electric power transmission lines 150 kV and 500 kV are known by the name of the Java-Madura-Bali System Interconnection. Thus, the balance of power throughout the province, Represented by the balance of power of the Java-Madura-Bali interconnection system, where in 2010 and 2011 systems are in good condition, whereas in 2012, 2013 and 2014 the capacity of the system can not meet That peak loads exist so That experiencing deficits.

Additional Electricity Infrastructure Plan

The assumption of population growth in Java Madura, Bali an estimated 1% per year and GDP growth for the same period is projected at 6.1% per year, so assuming the electric energy demand growth is expected to grow at an average of 10.0% per year.

In an effort to meet the needs of electricity in the province of Banten, it has been planned additional electricity infrastructure from the year 2010-2014 as follows:

  • Power plants of 2280 MW (about 925 MW is expected to be operational in 2010).
  • Transmission of electricity 1710 kms (including the Province of DKI Jakarta).
  • the Substation 15.244 MVA (including the Province of DKI Jakarta).
  • new renewable energy program (EBT) and network:
    • PLTS 50 WP is spread as much as 39,225 units.
    • Centralized PLTS 15 kW 8 units.
    • PLTMH 307 kW.
    • The 1640 distribution substation units (80,000 kVA)
    • Medium Voltage Network 4890 kms
    • Low Voltage Network 4360 kms.

West Java Province

System Conditions
Electrical systems in West Java province is a part of the system interconnection of Java-Madura-Bali. The main supply for electricity demand in West Java province, other than the transmission system 500 kV and 150 kV are Saguling Cirata hydropower and hydropower.
Currently electrification ratio of West Java Province has reached 67.40% and the ratio of electrified villages of 99.81%. While the waiting list has reached PLN 131 718 or 176.9 MVA request.

Balance of Power
Province of DKI Jakarta, Banten, West Java, Central Java, IN. Yogyakarta, East Java, and Bali have been well interconnected on electric power transmission lines 150 kV and 500 kV are known by the name of the Java-Madura-Bali System Interconnection. Thus, the balance of power throughout the province, Represented by the balance of power of the Java-Madura-Bali interconnection system, where in 2010 and 2011 systems are in good condition, whereas in 2012, 2013 and 2014 the capacity of the system can not meet That peak loads exist so That experiencing deficits.

Additional Electricity Infrastructure Plan

The assumption of population growth in Java Madura, Bali is estimated 1% per year and GDP growth for the same period is projected at 6.1% per year, so with that assumption the electric energy demand growth is expected to grow at an average of 10.0% per year.

In an effort to meet the needs of electric power in West Java Province, it has been planned additional electricity infrastructure from the year 2010-2014 as follows:

  • Power plants of 7538 MW (about 1102 MW is expected to be operational in 2010).
  • Transmission of electricity 2834 kms.
  • the substation 11 080 MVA.
  • new renewable energy program (EBT) and network:
    • PLTS 50 WP is spread as much as 34,825 units.
    • Centralized PLTS 15 kW 8 units.
    • PLTMH 400 kW.
    • The 1390 distribution substation units (69 500 kVA).
    • Medium Voltage Network 4120 kms
    • Low Voltage Network 4460 kms.

Banten Subsistem Network Map

West Java Subsystem Newwork Map :

 

 