NO NAME OWNER TYPE CAPACITY/MW TARGET OF COMPLETION
Aceh
1 PLTU NAD-Nagan Raya PLN-Sinahyono
Corporation
coal 2 X 110 2012
2 PLTA Peusangan I & II PT Pembangunan Perumahan/Hyundai hydro 2×22,5+2X21,5 2013+2014
3 PLTA Peusangan IV PT. Ingako Energy hydro 2 x 21.7 2018
4 GTG ex PT. Arun Local Government / Pemda gas 2 x 20 2011
5 PLTU Sinabang PLN coal 2 x 3 2012
6 PLTU Tapaktuan PLN coal 2 x 7 2012
7 PLTU Singkil PLN coal 2 x 3 2012
Bali
8 PLTU Celukan Bawang PT. General Energy Bali coal 1 x 130 + 1 x 250 2014
Bangka – Belitung
10 PLTU Tempilang (Cangkang) Bangka PT. Sawindo biomass 1 x 7 2010
11 PLTU Mempaya (cangkang) PT. Sawindo biomass 1 x 7 2010
12 PLTU Bangka Belitung 3 – Air Anyir PLN coal 3 x 30 2010-2011
13 PLTU Bangka Belitung 4 – Belitung / Suge PLN-PT Poeser
Indonesia
coal 2 x 16.5 2011
Banten
14 PLTU Suralaya # 8 PLN- CNTIC & PT.Rekayasa Industri coal 1 x 625 2011
15 PLTU Labuan PLN-Chengda Engineering Corp & PT. Truba Jurong Engineering coal 1 x 300 2010
16 PLTU Teluk Naga / Lontar PLN-Dongfang Electric Corporation PT. Dalle Energy coal 3 x 315 2011
17 PLTM Leuwikopo PT. Kutilang Paksi Mas hydro 2 x 2.6 2012
18 PLTM Cikamundung IPP hydro 5 2013
19 PLTM Cikidang PT. Cikidang Hydro hydro 2 2013
20 PLTM Cisono PT. Cisono Hydro hydro 3 2013
21 PLTM Cisungsang II PT. Cisungsang Hydro hydro 3 2013
22 PLTM Karang Ropong IPP hydro 6 2013
23 PLTM Lebak Tundun PT. Kutilang Paksi Mas hydro 2 x2.5 2013
24 PLTM Situmulya PT. Situmulya hydro 3 2013
Bengkulu
25 PLTM Lebong PT. Mega Power Mandiri m. hydro 4 x 3.0 2011
26 PLTM Simpang Aur 1 & 2 PT. Kutilang Paksi Mas m. hydro 2×6 + 2×9 2013
27 PLTM Manna PT. Manna Energy Pratama m. hydro 2 x 2.0 2011
Central Java
28 PLTU Rembang PLN-Zelan, Tronoh, Priamanaya coal 2 x 315 2011
29 PLTU Adipala PLN-CNTIC & Shanghai Electric Group coal 2 x 330 2014
30 PLTU Tanjung Jati B Exp Korea Midland Power Co coal 2 x 660 2012
Central Kalimantan
31 PLTU Pangkalan Bun PT. Central Korporindo International coal 2 x 7 2011
32 PLTU Pulang Pisau CNHMS & Mega Power coal 2 x 60 2012-2013
33 PLTU Sampit/FTP 2 PLN coal 2 x 25 2015
Central Sulawesi
34 PLTA Poso Energi PT. Poso Energi hydro 3 x 65 2012
35 PLTA Solewana I , II, III / Poso PT. Poso Energy hydro 3 x 65 2012
36 PLTM Sansarino PLN Pusharlis m. hydro 1 x 0.8 2010
37 PLTM Tomini II PLN Pusharlis m. hydro 2 x 1 2010
38 PLTM Sawidago II PLN Pusharlis m. hydro 1 x 1 2012
East Java
39 PLTU Pacitan PLN-Dongfang Electric Corporation & PT. Dalle Energy coal 2 x 315 2012
40 PLTU Paiton Baru PLN-Harbin Power Engineering, PT. Mitra Selaras Hutama Energi coal 1 x 660 2012
41 PLTU Tj. Awar-Awar PLN- SINOMACH, CNEEC, PT.Penta Adi Samudra coal 2 x 350 2013
42 PLTU Paiton # 3 Exp PT. Paiton Energy Company coal 1 x 815 2012
East Kalimantan
43 PLTU Tanah Grogot PT. Mahajaya Arya Satya coal 2 x 7 2013
East Nusatenggara
44 PLTP Ulumbu (APBN) PLN geothermal 4 x 2.5 2013-2014
PLTP Ulumbu (ADB) PLN geothermal 5 2012
45 PLTU NTT 2 – Kupang Baru FTP1 PLN-PT Poeser Indonesia coal 2 x 16.5 2012
46 PLTU Atambua kab Belu(APBN) PLN coal 4 x 6 2011
47 PLTU Rote Ndau PLN coal 2 x 3 2012
48 PLTU NTT-1 Ropa FTP 1 PLN coal 2 x 7 2012
49 PLTP Mataloko PLN geothermal 1 x 1.8 2011
50 PLTM Lewa IPP hydro 1 x0.85 2011
51 PLTM Lokomboro II IPP hydro 1 x 2 2011
52 PLTM Praikalala I IPP hydro 1 x 1 2011
53 PLTM Wae Roa – Ngada IPP hydro 1 x 0.4 2011
54 PLTM Umbuwangu I & II IPP hydro 2 x 1 2012
55 PLTM Praikalala II IPP hydro 1 x 0.5 2012
56 PLTM Lewa IPP hydro 1 x 0.5 2012
57 PLTM Lokomboro III IPP hydro 1 x 1.5 2012
58 PLTM Praikalala II IPP hydro 3 x 1 2013
59 PLTM Ndungga PLN m. hydro 2 x 0.95 2012
Gorontalo
60 PLTM Mongango PLN m. hydro 2 x 0.6 2011
61 PLTU Molotabu PT. Tenaga Listrik Gorontalo coal 2 x 10 2012
62 PLTU Gorontalo PT. Tenaga Listrik Gorontalo coal 2 x 6 2013
63 PLTU Gorontalo Baru / FTP1 PLN-Meta Epsi coal 2 x 25 2011
64 PLTU Gorontalo Baru / FTP2 PLN & PT Reka Daya Electrika coal 2 x 25 2012
Jakarta
65 PLTGU Muara Karang repowering PLN – Java Bali Generation Unit / PT. PJB gas 1×210 2011
66 PLTGU Priok extension PLN gas 1×500 + 1×243 2012-2013
Jambi
67 PLTU Semaran – Sarolangun PT. Permata Indo Cemerlang Sejahtera coal 2 x 7 2010
Lampung
68 PLTU Kalianda PT. Kalianda Kita Jaya coal 2 x 6 2013
69 PLTU Lampung Tengah PT. Sepoetih Daya Prima coal 2 x 6 2013
70 PLTP Ulubelu 1 & 2 PT. Pertamina Geothermal Energy geothermal 2 x 55 2011-2012
71 PLTU Tarahan   FTP 1 PLN-PT Adi Karya coal 2 x 100 2011
Maluku
72 PLTU Maluku – Ambon Baru FTP1 PLN coal 2 x 15 2013
73 PLTP Tulehu PLN geothermal 2 x 10 2015
PLTU Waai /FTP 1 PLN coal 2 x 15 2013
North Maluku
74 PLTM Goal IPP m. hydro 2 x 0.75 2011
75 PLTU Tidore – FTP 1 PLN coal 2 x 7 2011
North Sulawesi
76 PLTU Sulut 2 – Manado FTP 1 PLN coal 2 x 25 2011
77 PLTU Sulut 2-Amurang FTP 1 PLN coal 2 x 25 2014
78 PLTP Lahendong IV Pertamina Geothermal Energy geothermal 1 x 20 2011
79 PLTP Lahendong V-FTP 2 Pertamina Geothermal Energy geothermal 1 x 20 2014
80 PLTP Lahendong VI FTP 2 Pertamina Geothermal Energy geothermal 1 x 20 2015
81 PLTA Poigar II PLN hydro 2 x 15 2011
82 PLTM Lobong I PLN m. hydro 1 x 1.6 2011
North Sumatera
83 PLTA Asahan I PT Bajradaya & China Huadian Eng Corp hydro 2 x 90 2010
84 PLTM Hutaraja PT. Humbahas Bumi Energi m. hydro 2 x 3 2011
85 PLTM Parlilitan PT. Aek Simanggo energi m. hydro 3 x 2.5 2010
86 PLTM Silau 2 PT. Bersaudara Simalungun Energi m. hydro 3 x 2.5 2010
87 PLTM Parluasan PT. Inpola Meka elektrindo m. hydro 2 x 2.1 2012
Papua
88 PLTA Genyem PLN hydro 2 x 10 2012-2013
89 PLTU Papua 2 – Jayapura Baru FTP1 PLN-Modern Widya-
Boustead Maxitherm
Industries
coal 2 x 10 2011
90 PLTU Papua 1 – Timika FTP1 PLN coal 2 x 7 2012
91 PLTM Walesi II PT Bumi Cendrawasih Jayawijaya. m. hydro 6 x 1 2012
Riau
92 PLTU Rengat PT. Central Korporindo coal 2 x 7 2013
93 PLTU Tembilahan PLN coal 2 x 7 2013
94 PLTU Bengkalis/Riau 1 FTP 1 PLN coal 2 x 10 2011
95 PLTU Selat Panjang/Riau 2 PLN-PT Boulevard coal 2 x 7 2011
Riau Islands
96 PLTU Tanjung Pinang 1 IPP coal 2 x 10.8 2013
97 PLTU Tanjung Balai Karimun PT. Listrik Nusantara Karimun coal 2 x 6 2013
98 PLTU Tanjung Balai Karimun PLN coal 2 x 7 2010-2011
South East Sulawesi
99 PLTM Ratelimbong – Kolaka PLN m. hydro 2 x 1.2 2012
100 PLTM Sabilambo – Kolaka PLN m. hydro 2 x 2 2012-2018
101 PLTM Rongi PLN m. hydro 1 x 1.8 2012
South Kalimantan
102 PLTU Kalsel Asam-Asam/FTP1 PLN-Wijaya Karya -
Chengda
coal 2 x 65 2011
103 PLTU Kota Baru APBN PLN coal 2 x 7 2013
104 PLTU Muara Jawa/Teluk Balikpapan/FTP1 PLN coal 2 x 110 2014
105 PLTG Kaltim /FTP 2 PLN gas 2 x 100 2016
106 PLTG Kaltim Peaking/APBN PLN gas 2 x 50 2018
South Sulawesi
107 PLTM Ranteballa PT. Fajar Futura Energy m. hydro 2 x 1.2 2010
108 PLTM Manipi / Tangka 1 PT. Sulawesi Mini Hydro m. hydro 1 x 3.5 2011
109 PLTM Manipi / Tangka 2 PT. Sulawesi Mini Hydro m. hydro 1 x 7.5 2011
110 PLTU Sulsel 1 – Jeneponto PT Bosowa Energy coal 2 x 100 2012-2013
111 PLTU Sulawesi Selatan – Barru/FTP1 PLN-Hubai – Bagus
Karya
coal 2 x 50 2011
112 PLTGU Sengkang PT. Energy Sengkang gas 2 x 60 2011
South Sumatera
113 PLTU Simpang Belimbing PT. Guo Hua Energy Musi Makmur coal 2 x 113.5 2011
114 PLTU Banjarsari PT. Bukit Pembangkit Inovatif coal 2 x 100 2014
115 PLTU Sumsel 2 (Keban Agung) PT. Priamanaya Power Energy coal 2 x 112.5 2015
116 PLTGU Keramasan PLN gas 86 2011
West Java
117 PLTGU Muara Tawar Blok 5 PLN gas 1×234 2011
118 PLTU Pelabuhan Ratu PLN – Shanghai Electric Group CO, LTD & Maxima Infrastructure (Truba) coal 3 x 350 2012-2013
119 PLTU Indramayu PLN-SINOMACH, CNEEC, PT.Penta Adi Samudra coal 3 x 330 2011
120 PLTP Kamojang # 4 PT. Pertamina Geothermal energi geothermal 1 x 60 2013
121 PLTP Wayang Windu PT. Star Energi geothermal 1 x 120 2012
122 PLTG Bekasi Power PT. Bekasi Power gas 1 x 130 2010
123 PLTG Cikarang Listrindo PT. Cikarang Listrindo gas 1 x 100 + 1 x 50 2010-2011
124 PLTU Cirebon PT. Cirebon Electric Power coal 1 x 660 2011
West Kalimantan
125 PLTM Merasap PLN m. hydro 1 x 1.5 2010
126 PLTU Ketapang PT. Mahajaya Arta Satya coal 2 x 7 2013
127 PLTU Pontianak 2 PT. Equator Manunggal Power coal 2 x 25 2013
128 PLTU Kalbar 1 – Parit Baru-Perpres 1 PLN – Praba Group & Gezhouba Group-China coal 2 x 50 2012
129 PLTU Kalbar 2 – pantai kura2 – Tanjung Gundul Bengkayang PLN-Cons Indofuji, Guangdong, Persada Inti – Advance Technology coal 2 x 27.5 2012
West Nusatenggara
130 PLTU Lombok (APBN) PLN coal 1 x 25 2010
131 PLTM Santong PLN m. hydro 1 x 0.85 2011
132 PLTU NTB 1 – Bima/Sumbawa FTP 1 PLN coal 2 x 10 2011
133 PLTU NTB 2 – Lombok Baru FTP1 PLN coal 2 x 25 2011
134
West Papua
135 PLTM Prafi PLN m. hydro 1 x 2.5 2013
West Sulawesi
136 PLTM Balla PLN m. hydro 1 x 1 2010
137 PLTM Bonehau PLN m. hydro 2 x 2 2010
138 PLTM Budong-Budong PLN m. hydro 2 x 1 2010
139 PLTM Kalukku PLN m. hydro 2 x 0.5 2010
West Sumatera
140 PLTM Manggani IPP m. hydro 1 x 1.1 2010
141 PLTU Sumbar Pesisir/FTP 1 PLN coal 2 x 112 2012